20260805-item-02-5---offer-verification-exception-request-timeline-defintion---pjm-proposal.pdf
Who says it Issuer not stated on the document
Document role not classified
Docket —
Document date Jul 30, 2026
Retrieved 2026-07-30 12:04 UTC
Fingerprint bed75abd137618ca4c109ce140b1b8d7e8656f8df733c36274bb2299c5085c0d
Official copy at the source ↗
What Gridlight cited from it
The passages below are the spans Gridlight's claims rest on, matched against the archived bytes whose fingerprint is above. They are excerpts, not the document.
PJM's Market Implementation Committee takes up a 60-calendar-day offer-verification exception timeline claim 3 p. 5
…ement, Schedule 1, section 3.2.3(r) (r) Market Sellers that incur incremental operating costs for a generation resource that are either greater than $1,000/MWh as determined in accordance with the Market Seller's PJM-approved Fuel Cost Policy, Operating Agreement, Schedule 2 and PJM Manual 15, but are not verified at the time of dispatch of the resource under section 6.4.3 of this Schedule, or greater than $2,000/MWh as determined in accordance with the Market Seller's PJM-approved Fuel Cost Policy, Operating Agreement, Schedule 2, and PJM Manual 15, will be eligible to receive credit for Operating Reserves upon review of the Market Monitoring Unit and the Office of the Interconnection, and approval of the Office of the Interconnection. Market Sellers must submit to the Offic…
Gridlight archives the full document so its quotes can be checked against unchanging bytes, and serves the cited passages here. The complete document is available at the official link above.
Gridlight verifies that quoted and cited material matches the archived source document. It does not independently verify that the source’s statements are true.