RM21-17: Order 1920 compliance filings due Feb 12, 2027
PJM BRIEF

PJM's Market Implementation Committee takes up a 60-calendar-day offer-verification exception timeline

PJM's Issue Charge would use the Quick Fix process to align Manual 11's offer-verification exception deadline to 60 calendar days, with committee work set to start immediately and run two months, ahead of winter operations.

The current timeline described in Attachment D of 11:00 AM EPT the next business day is burdensome for Market Sellers, who must also work on current and future days' offer submissions during ongoing winter events.1

The executive summary describes the change as aligning Manual 11 Attachment D and Section 2.3.6.2 — covering offers over $1,000/MWh — to the same 60-calendar-day exception-request timeline.2

Under PJM's Operating Agreement, Schedule 1, section 3.2.3(r), a Market Seller's incremental operating costs that exceed $1,000/MWh and are not verified at the time of dispatch of the resource — or that exceed $2,000/MWh regardless of verification — are eligible for Operating Reserve credit only after review by the Market Monitoring Unit and approval by PJM's Office of the Interconnection.3

PJM's Issue Charge states that this issue will use the Quick Fix process and will be assigned to the Market Implementation Committee (MIC) for Issue Charge approval and solution endorsement, per Manual 34 section 8.6.1.4

The work is planned to start immediately and run two months in duration at MIC, with the aim of having a solution in place before winter operations, when Offer Verification activity is likely.5

Coverage notes

Gridlight’s notes on what we looked for and did not find; these statements are Gridlight’s own and are not claim-checked against archived sources.

  • This piece does not describe any MIC member reaction to PJM's proposed 60-day timeline, or any competing redline — the documents show only PJM's proposed text.
  • This piece does not address whether the manual change requires a conforming Operating Agreement or Tariff change; the Issue Charge lists tariff/OA modifications as out of scope for the Quick Fix process, while PJM's proposal cites OA Schedule 1 section 3.2.3(r) as underlying authority, and the documents do not reconcile the two.
  • This piece does not include a response from the Independent Market Monitor, Market Sellers, or other stakeholders to PJM's proposed timeline; none appears in the documents.
Sources 5/5 matched to archived source ✓
1 20260805-item-02-1---offer-verification-exception-request-timeline-defintion---problem-statement.pdf Jul 30, 2026 archived ↗
2 20260805-item-02-2---offer-verification-exception-request-timeline-defintion---issue-charge.pdf Jul 30, 2026 archived ↗
3 20260805-item-02-4---offer-verification-exception-request-timeline-defintion---executive-summary.pdf Jul 30, 2026 archived ↗
4 20260805-item-02-5---offer-verification-exception-request-timeline-defintion---pjm-proposal.pdf Jul 30, 2026 archived ↗