Every cited factual claim resolves to a primary source — tap a mark to see the source ■ 27 briefs
RM21-17: Order 1920 compliance filings due Feb 12, 2027
PJM BRIEF

PJM's Manual 6 Revision 35 reaches MRC for first read

The annual periodic review carries a conforming interconnection-reform change and takes effect September 24, 2026.

Revision 35 to Manual 6 is the manual's annual periodic review, conducted per the process specified in Manual 34.1

Manual 6 Revision 35 conforming changes stem from a tariff filing under Section 35.13(a)(2)(iii) for Interconnection Reform, FERC Docket ER22-2110.2

The MRC 1 read date is August 19, 2026.3

Revision 35, effective 09/24/2026, adds conforming language to Section 4.9.3 indicating that the form provided in the PJM Tariff, Part IX, Subpart K, Upgrade Application and Studies Agreement, should be used for the IARRs request, per ER22-2110.4

PJM's Manual 06, Revision 35, sets September 24, 2026 as its effective date.5

Coverage notes

Gridlight’s notes on what we looked for and did not find; these statements are Gridlight’s own and are not claim-checked against archived sources.

  • Whether the Markets and Reliability Committee actually votes to endorse Revision 35 on September 24, 2026 is not established by these documents, which show only the scheduled date.
  • Whether the presentation's reference to 'administrative changes throughout the manual' extends beyond Section 4.9.3 is not established; the redline's revision history documents only that one substantive change.
  • Whether the broader FERC Docket ER22-2110 Interconnection Reform proceeding has itself concluded is not addressed by these documents, which cover only this conforming manual edit.
Sources 5/5 matched to archived source ✓
1 20260819-item-08a--1-manual-06-revisions---presentation.pdf Sep 4, 2026 archived ↗
2 20260819-item-08a--2-manual-06-revisions---executive-summary.pdf Sep 4, 2026 archived ↗
3 20260819-item-08a--3-manual-06-revisions---redlines.pdf Sep 4, 2026 archived ↗